Yeah, I thought that it would grab attention.

We are a little ahead of schedule. I have the ceilings done, as planned for today, but I also have the walls done as well. I am shooting for primer on everything tomorrow (I'll have to leave work early). Then, hopefully, the bathroom can be sanded and textured on Wednesday. Tile has been pushed to next Monday, with grout on next Tuesday, and carpet is next Wednesday. We are starting to think that we should stain all of the door and window frames before the carpet comes, which I should be able to do next Monday since that will just be tile work with an extra day to make sure that I get it all done.

I enjoy the project, but I am honestly ready for some time off from it. I was told by my father-in-law that we wouldn't be able to get it all done before the first weekend in August when we have 10 other people visiting, so of course, I felt that it was a challenge. I can't wait to prove him wrong, but I also can't wait to just be done.


Farewell - June 4, 2020